Since May 13, 2025 the following project highlights have occurred:
- Site and earthworks RFP posted on BC Bid, closes June 13th; Ministry advised.
- Site and earthworks tender drawings were delivered to the City to be reviewed for the building permit.
- Principal Richer formed an Expansion Committee made up of school staff, custodian and Health and Safety Coordinator to plan for construction and impacts. Questions and items of discussion were forwarded to Director of Operations and Secretary-Treasurer.
- Director of Operations and Secretary-Treasurer attended a voluntary school staff meeting to answer questions above and discuss plans and schedule.
- Fort Modular construction of the modular units commenced.
- Mandatory site visit for the site and earthworks tender proponents.
- Director of Operations and Facilities Manager met with City of Dawson Creek to provide an update on the project.
Budget spent to date: $1,156,737 (12.5%)
Please follow Capital Projects for updates and further information on this project.