Key highlights since June 12, 2025
- Tender 2 awarded to Northern Legendary Construction.
- Building permit for foundation was issued by the City.= of Dawson Creek.
- Start-up meeting was held at Crescent Park with Force Engineering, SD59 and Northern Legendary.
- Northern Legendary started earthwork.
- Secretary-Treasurer applied to the Ministry for the “below the line” funding for the project.
- Northern Legendary worked fast and efficiently to get the pilings completed for the retaining wall, and the foundation on which the modular sections would be placed. Sprinkler lines were also installed in the existing school.
- First “below the line funding” request was approved by the Ministry $1.3m
- First 2 modules for the expansion arrived on site.
- A logistics meeting was held on site to prepare for students’ return to the school in September and planning site access while the modules are getting placed. Representatives from SD59, staff School Administration, Fort Modular, Northern Legendary and Force Engineering attended the meeting.
- Fort Modular placed the modules between August 28 - August 31.
- Fort Modular and Northern Legendary began working on joining the modular sections together.
- Fort Modular Project Manager visited the job site to do an inspection and solve a few alignment issues.
Please follow https://www.sd59.bc.ca/district/capital-projects for updates on the project.