The Crescent Park Expansion project team has moved the occupancy date to the summer 2026 due to the delay of the civil work until the spring because of the higher risks involved to complete during winter months.
Further updates included the Notice of Substantial Completion was issued to Fort Modular and Director of Operations and Secretary-Treasurer met with engineer to review and update the project budget and discussed a plan to remediate current deficiencies.
Full updates on the capital projects are available at https://www.sd59.bc.ca/district/capital-projects.