The following project updates occurring since the last meeting:
• BC Hydro confirmed SD59 will have to give BC Hydro a right of way for the new service. BC Hydro has started the paperwork.
• Civil work was awarded to Northern Legendary.
• Work continued in the interior of the addition
• Fence was installed on top of the retaining wall
• Water and sewer work will begin as soon as the ground is thawed
Costs to date are within budget and the Board’s capital bylaw, including contingency.